Tandice, Kandivali West

Lapsed

by Manish Mahesh Dholakia · Kandivali West, Mumbai 400067 · Map

Launched
Aug 20171 yr 11 mths originally promised
Possession (MahaRERA)
Sep 2025Extended by 6 yrs 2 mthsWhat does Lapsed mean?
Concrete structure
90%Mid-construction
Booked
29 of 3583%
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
35
Total units
35
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)90%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 90%Jul 2026: Concrete structure (RCC) 90%Oct 2026: Concrete structure (RCC) 90%Dec 2024: Final finishes 60%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 90%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%90%60%29
100%90%0%–
100%90%0%–
100%100%60%29

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Tandice by Manish Mahesh Dholakia is a 35-unit project in Kandivali West, Mumbai 400067, launched in August 2017; its MahaRERA registration has lapsed. 29 units booked out of total 35 units. The concrete structure (RCC) is 90% complete.

Read full summary

Tandice is a project by Manish Mahesh Dholakia in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800010353. It was launched in August 2017. It has 35 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in September 2025, after an extension of 6 years 2 months from the original July 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 90% complete, final finishes 60% complete.

29 units booked out of total 35 units (83%).