Chembur Manshanti Chsl, Chembur
Ready to moveLapsed
by Menorah Realties Private Limited · Chembur, Mumbai 400071 · Map
- Launched
- Aug 20176 yrs 4 mths promised
- Possession (MahaRERA)
- Dec 2023Not extendedWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 36 of 4875%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 48
- Total units
- 48
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 36 | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | – | |
| 100% | 100% | 95% | 36 |
"–" means MahaRERA shows no figure for that update.
About this project
Chembur Manshanti Chsl by Menorah Realties Private Limited is a 48-unit project in Chembur, Mumbai 400071, launched in August 2017; its MahaRERA registration has lapsed. 36 units booked out of total 48 units. The concrete structure (RCC) is complete.
Read full summary
Chembur Manshanti Chsl is a project by Menorah Realties Private Limited in Chembur, Mumbai 400071, registered with MahaRERA as P51800010509. It was launched in August 2017. It has 48 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2023. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
36 units booked out of total 48 units (75%).