Nirmal Lifestyle-Amethyst, Mulund West

Lapsed

by Nirmal Lifestyle Ltd · Mulund West, Mumbai 400080 · Map

Launched
Aug 20171 yr 7 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 6 yrs 9 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
1 of 1100%
Buildings
10.2 acres
MahaRERA complaints
9Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
1
Total units
1
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services4%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 71%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 4%Jul 2026: Final finishes 4%Oct 2026: Final finishes 4%Excavation 100%Concrete structure (RCC) 100%Final finishes 4%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%4%1
100%100%4%1
100%100%4%–
100%71%0%252

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Nirmal Lifestyle-Amethyst by Nirmal Lifestyle Ltd is a 1-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in August 2017; its MahaRERA registration has lapsed. 1 unit booked out of total 1 unit. The concrete structure (RCC) is complete.

Read full summary

Nirmal Lifestyle-Amethyst is a BMC-sanctioned project by Nirmal Lifestyle Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800010841. It was launched in August 2017. It has 1 unit in 1 building, with 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 6 years 9 months from the original March 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 4% complete.

1 unit booked out of total 1 unit (100%).