Sham Nirmal Heights, Malad West

Ready to move

by Altaa Buiilders · Malad West, Mumbai 400064 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Apr 2027Extended by 4 yrs 4 mths
Concrete structure
100%Ready to move
Booked (free sale)
46 of 4798% · 1 rehab units
Buildings
20.8 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale46 booked out of 47 units

Rehab1 unit for existing members

Total 48 units. Rehab units are not for sale.

Project facts

1 BHK
7
2 BHK
11
3 BHK
23
Other units
7
Total units
48
Buildings
2
Land
0.8 acres
Phases
1
MahaRERA complaints
3
Free-sale units
47
Rehab units
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 43%Dec 2025: Final finishes 80%Jul 2026: Final finishes 91%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%46
100%100%91%36
100%100%80%35
100%100%43%32

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 20–90 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths3 yrs 6 mths
Possession date extendedBy 4 yrs 4 mths5 of 6
Possession date (MahaRERA)Apr 2027Jan 2025
Concrete structure (RCC)100%100%
Units booked (free sale)98%42%
MahaRERA complaints (filed by or against the builder)32

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Sham Nirmal Heights by Altaa Buiilders is a 48-unit BMC-sanctioned project in Malad West, Mumbai 400064, launched in August 2017 with possession due in April 2027. 46 units booked out of 47 units for sale. The concrete structure (RCC) is complete.

Read full summary

Sham Nirmal Heights is a BMC-sanctioned project by Altaa Buiilders in Malad West, Mumbai 400064, registered with MahaRERA as P51800010872. It was launched in August 2017. It has 48 units in 2 buildings: 41 homes (1, 2 and 3 BHK) and 7 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 48 units, 47 are for sale and 1 is a rehab unit for existing members.

Its registered possession date is April 2027, extended by 4 years 4 months from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

46 units booked out of 47 units for sale (98%). Since the July 2026 update, 10 more units have been booked and the possession date has moved from June 2023 to April 2027.