Deep Darshani Chs, Malad West

Lapsed

by Sarvoday Builders and Developers · Malad West, Mumbai 400064 · Map

Launched
Aug 20174 yrs 4 mths originally promised
Possession (MahaRERA)
Jul 2026Extended by 4 yrs 7 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
1 of 323%
Buildings
10.2 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
32
Total units
32
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 100%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%0%1
100%100%0%–
100%100%0%–
100%0%0%1

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400064

Projects with 10–70 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400064
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 4 mths2 yrs 8 mths
Possession date extendedBy 4 yrs 7 mths5 of 6
Possession date (MahaRERA)Jul 2026Nov 2025
Concrete structure (RCC)100%95%
Units booked3%80%
MahaRERA complaints (filed by or against the builder)44

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Deep Darshani Chs by Sarvoday Builders and Developers is a 32-unit project in Malad West, Mumbai 400064, launched in August 2017; its MahaRERA registration has lapsed. 1 unit booked out of total 32 units. The concrete structure (RCC) is complete.

Read full summary

Deep Darshani Chs is a project by Sarvoday Builders and Developers in Malad West, Mumbai 400064, registered with MahaRERA as P51800005117. It was launched in August 2017. It has 32 units in 1 building, with 1 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in July 2026, after an extension of 4 years 7 months from the original December 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes not started.

1 unit booked out of total 32 units (3%).