- Launched
- Aug 20171 yr 11 mths originally promised
- Possession (MahaRERA)
- Jan 2021Extended by 1 yr 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 23 of 3174%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 15Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1
- 3 BHK
- 29
- 5+ BHK
- 1
- Total units
- 31
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 15
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 60% | 23 | |
| 50% | 50% | 30% | – | |
| 50% | 50% | 30% | – | |
| 100% | 100% | 60% | 23 |
"–" means MahaRERA shows no figure for that update.
About this project
Ganga Jamna Sangam by Parthesh Developers is a 31-unit project in Khar West, Mumbai 400052, launched in August 2017; its MahaRERA registration has lapsed. 23 units booked out of total 31 units. The concrete structure (RCC) is complete.
Read full summary
Ganga Jamna Sangam is a project by Parthesh Developers in Khar West, Mumbai 400052, registered with MahaRERA as P51800010901. It was launched in August 2017. It has 31 units in 1 building, with 1, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in January 2021, after an extension of 1 year 6 months from the original July 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.
23 units booked out of total 31 units (74%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 50% to 100% and the possession date has moved from July 2020 to January 2021.