Ganga Jamna Sangam, Khar West

Lapsed

by Parthesh Developers · Khar West, Mumbai 400052 · Map

Launched
Aug 20171 yr 11 mths originally promised
Possession (MahaRERA)
Jan 2021Extended by 1 yr 6 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
23 of 3174%
Buildings
10.3 acres
MahaRERA complaints
15Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
1
3 BHK
29
5+ BHK
1
Total units
31
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
15

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 50%Jul 2026: Excavation 50%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 50%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 60%Dec 2025: Final finishes 30%Jul 2026: Final finishes 30%Oct 2026: Final finishes 60%Excavation 100%Concrete structure (RCC) 100%Final finishes 60%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%60%23
50%50%30%–
50%50%30%–
100%100%60%23

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Ganga Jamna Sangam by Parthesh Developers is a 31-unit project in Khar West, Mumbai 400052, launched in August 2017; its MahaRERA registration has lapsed. 23 units booked out of total 31 units. The concrete structure (RCC) is complete.

Read full summary

Ganga Jamna Sangam is a project by Parthesh Developers in Khar West, Mumbai 400052, registered with MahaRERA as P51800010901. It was launched in August 2017. It has 31 units in 1 building, with 1, 3 and 5+ BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in January 2021, after an extension of 1 year 6 months from the original July 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 60% complete.

23 units booked out of total 31 units (74%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 50% to 100% and the possession date has moved from July 2020 to January 2021.