Balaji Apartment, Mulund West
Ready to move
by Tridev Realty And Construction Pvt Ltd · Mulund West, Mumbai 400080 · Map
- Launched
- Aug 20176 yrs 4 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 3 yrs 4 mths
- Concrete structure
- 100%Ready to move
- Booked
- 60 of 6790%
- Buildings
- 10.4 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 5
- 2 BHK
- 14
- 3 BHK
- 6
- 4 BHK
- 5
- 5+ BHK
- 1
- Other units
- 36
- Total units
- 67
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 99% | 60 | |
| 100% | 100% | 99% | – | |
| 100% | 100% | 99% | – | |
| 100% | 100% | 73% | 60 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400080
Projects with 10–70 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 6 yrs 4 mths | 4 yrs 1 mth |
| Possession date extended | By 3 yrs 4 mths | 5 of 6 |
| Possession date (MahaRERA) | Apr 2027 | Aug 2026 |
| Concrete structure (RCC) | 100% | 100% |
| Units booked | 90% | 95% |
| MahaRERA complaints (filed by or against the builder) | 0 | 0 |
The 6 projects
- Shree Laxminarayan Enclave, Mulund West
- Aakruti Aashvi Apartment, Mulund West
- Meghdoot, Mulund West
- N And G Co Op Housing Soc Ltd, Mulund West
- Mulund Narayan Pushp Chs Ltd, Mulund West
- Maverick Mooldeep, Mulund West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Shree Laxminarayan Enclave | August 2017 | December 2021 | 0% | 18 units booked out of total 30 units |
| Aakruti Aashvi Apartment | August 2017 | June 2026 | 100% | 28 units booked out of total 36 units |
| Meghdoot | August 2017 | December 2026 | 98% | 90 units booked out of total 93 units |
| N And G Co Op Housing Soc Ltd | August 2017 | March 2027 | 100% | 20 units booked out of 21 units for sale |
| Mulund Narayan Pushp Chs Ltd | August 2017 | August 2024 | 100% | 20 units booked out of total 21 units |
| Maverick Mooldeep | August 2017 | October 2026 | 100% | 26 units booked out of 27 units for sale |
About this project
Balaji Apartment by Tridev Realty And Construction Pvt Ltd is a 67-unit project in Mulund West, Mumbai 400080, launched in August 2017 with possession due in April 2027. 60 units booked out of total 67 units. The concrete structure (RCC) is complete.
Read full summary
Balaji Apartment is a project by Tridev Realty And Construction Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800011083. It was launched in August 2017. It has 67 units in 1 building: 31 homes (1, 2, 3, 4 and 5+ BHK) and 36 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 3 years 4 months from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
60 units booked out of total 67 units (90%).