Maverick Mooldeep, Mulund West

Ready to moveLapsed

by Maverick Realtors · Mulund West, Mumbai 400080 · Map

Launched
Aug 20175 yrs 4 mths originally promised
Possession (MahaRERA)
Oct 2026Extended by 3 yrs 10 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
26 of 2796% · 36 rehab units
Buildings
10.3 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale26 booked out of 27 units

Rehab36 units for existing members

Total 63 units. Rehab units are not for sale.

Project facts

1 RK
2
1 BHK
3
2 BHK
15
3 BHK
32
Other units
11
Total units
63
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
2
Free-sale units
27
Rehab units
36

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services98%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 98%Excavation 100%Concrete structure (RCC) 100%Final finishes 98%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%98%26
100%100%90%14
100%100%90%–
100%100%0%17

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 20–150 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)5 yrs 4 mths4 yrs 9 mths
Possession date extendedBy 3 yrs 10 mths6 of 6
Possession date (MahaRERA)Oct 2026Dec 2026
Concrete structure (RCC)100%100%
Units booked (free sale)96%90%
MahaRERA complaints (filed by or against the builder)20

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Maverick Mooldeep by Maverick Realtors is a 63-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in August 2017; its MahaRERA registration has lapsed. 26 units booked out of 27 units for sale. The concrete structure (RCC) is complete.

Read full summary

Maverick Mooldeep is an SRA-sanctioned project by Maverick Realtors in Mulund West, Mumbai 400080, registered with MahaRERA as P51800003963. It was launched in August 2017. It has 63 units in 1 building: 52 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 11 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 63 units, 27 are for sale and 36 are rehab units for existing members.

Its registered possession date is October 2026, extended by 3 years 10 months from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes 98% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

26 units booked out of 27 units for sale (96%). Since the July 2026 update, 12 more units have been booked and the possession date has moved from December 2023 to October 2026.