A-2, Andheri West

Lapsed

by Parikh Enterprise · Andheri West, Mumbai 400053 · Map

Launched
Aug 20178 yrs 4 mths promised
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
3
1 BHK
3
3 BHK
34
4 BHK
1
Total units
41
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation95%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 95%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Concrete structure (RCC) 100%Excavation 95%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%100%50%–
95%100%50%–
95%100%50%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

A-2 by Parikh Enterprise is a 41-unit project in Andheri West, Mumbai 400053, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

A-2 is a project by Parikh Enterprise in Andheri West, Mumbai 400053, registered with MahaRERA as P51800011193. It was launched in August 2017. It has 41 units in 1 building, with 1 RK, 1 BHK, 3 BHK and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025. That date has passed and no extension has been recorded. Construction: excavation 95% complete, structure (RCC) complete, final finishes 50% complete.