Dindoshi Sai Sadan Chs Ltd, Malad East

Lapsed

by Sanjay Bajranglal Agarwal · Malad East, Mumbai 400097 · Map

Launched
Aug 20173 yrs 10 mths originally promised
Possession (MahaRERA)
Jun 2022Extended by 1 yrWhat does Lapsed mean?
Concrete structure
23%Mid-construction
Booked
–
Buildings
10.3 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
76
Total units
76
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)23%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 23%Dec 2025: Concrete structure (RCC) 23%Jul 2026: Concrete structure (RCC) 23%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 23%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%23%0%–
100%23%0%–
100%23%0%15

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Dindoshi Sai Sadan Chs Ltd by Sanjay Bajranglal Agarwal is a 76-unit project in Malad East, Mumbai 400097, launched in August 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 23% complete.

Read full summary

Dindoshi Sai Sadan Chs Ltd is a project by Sanjay Bajranglal Agarwal in Malad East, Mumbai 400097, registered with MahaRERA as P51800011217. It was launched in August 2017. It has 76 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2022, after an extension of 1 year from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 23% complete, final finishes not started.