Bhavani Plaza, Bhandup West

by Padmakar Purushottam Gokarna · Bhandup West, Mumbai 400078 · Map

Launched
Aug 20172 yrs 4 mths originally promised
Possession (MahaRERA)
Oct 2027Extended by 7 yrs 10 mths
Concrete structure
97%Mid-construction
Booked (free sale)
24 of 24100% · 19 rehab units
Buildings
10.2 acres
MahaRERA complaints
10Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale24 booked out of 24 units

Rehab19 units for existing members

Total 43 units. Rehab units are not for sale.

Project facts

1 RK
4
1 BHK
18
2 BHK
16
3 BHK
2
Other units
3
Total units
43
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
10
Free-sale units
24
Rehab units
19

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)97%
Finishes, lifts and services97%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 70%Dec 2025: Concrete structure (RCC) 70%Jul 2026: Concrete structure (RCC) 97%Oct 2026: Concrete structure (RCC) 97%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 97%Oct 2026: Final finishes 97%Excavation 100%Concrete structure (RCC) 97%Final finishes 97%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%97%97%24
100%97%97%24
100%70%80%24
100%70%80%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 5 similar projects in PIN 400078

Projects with 20–80 flats, launched within 6 months of this one.

Compared with 5 similar projects in PIN 400078
MeasureThis projectSimilar projects
Launch to possession (as first promised)2 yrs 4 mths3 yrs 11 mths
Possession date extendedBy 7 yrs 10 mths5 of 5
Possession date (MahaRERA)Oct 2027Dec 2025
Concrete structure (RCC)97%100%
Units booked (free sale)100%64%
MahaRERA complaints (filed by or against the builder)101

The 5 projects

Other phases of this project are not included in the similar projects.

About this project

Bhavani Plaza by Padmakar Purushottam Gokarna is a 43-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, launched in August 2017 with possession due in October 2027. 24 units booked out of 24 units for sale. The concrete structure (RCC) is 97% complete.

Read full summary

Bhavani Plaza is a BMC-sanctioned project by Padmakar Purushottam Gokarna in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800011262. It was launched in August 2017. It has 43 units in 1 building: 40 homes (1 RK, 1 BHK, 2 BHK and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 43 units, 24 are for sale and 19 are rehab units for existing members.

Its registered possession date is October 2027, extended by 7 years 10 months from the original December 2019. Construction: excavation complete, structure (RCC) 97% complete, final finishes 97% complete.

24 units booked out of 24 units for sale (100%).