- Launched
- Aug 20171 yr originally promised
- Possession (MahaRERA)
- Feb 2023Extended by 4 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 13%Mid-construction
- Booked
- 41 of 5871%
- Buildings
- 10.4 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 38
- 2 BHK
- 19
- Other units
- 1
- Total units
- 58
- Buildings
- 1
- Land
- 0.4 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 13% | 30% | 41 | |
| 100% | 13% | 30% | – | |
| 100% | 13% | 30% | – | |
| 100% | 13% | 30% | 41 |
"–" means MahaRERA shows no figure for that update.
Compared with 6 similar projects in PIN 400078
Projects with 20–150 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr | 4 yrs 2 mths |
| Possession date extended | By 4 yrs 6 mths | 6 of 6 |
| Possession date (MahaRERA) | Feb 2023 | Jun 2026 |
| Concrete structure (RCC) | 13% | 98% |
| Units booked | 71% | 72% |
| MahaRERA complaints (filed by or against the builder) | 1 | 2 |
The 6 projects
- Bhavani Plaza, Bhandup West
- Skicity Phase 1, Bhandup West
- Dp Star Trinetra, Bhandup West
- Joys Adinath Tower II Wing A, Bhandup West
- Asiad, Bhandup West
- Bhandup Citizen CHS Ltd, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Bhavani Plaza | August 2017 | October 2027 | 97% | 24 units booked out of 24 units for sale |
| Skicity Phase 1 | August 2017 | December 2026 | 100% | 93 units booked out of total 162 units |
| Dp Star Trinetra | August 2017 | December 2024 | 8% | – |
| Joys Adinath Tower II Wing A | July 2017 | December 2025 | 100% | 53 units booked out of total 61 units |
| Asiad | January 2018 | October 2024 | 0% | – |
| Bhandup Citizen CHS Ltd | January 2018 | March 2028 | 100% | 0 units booked out of 38 units for sale |
About this project
Tirupati Height by Tirupati developer is a 58-unit project in Bhandup West, Mumbai 400078, launched in August 2017; its MahaRERA registration has lapsed. 41 units booked out of total 58 units. The concrete structure (RCC) is 13% complete.
Read full summary
Tirupati Height is a project by Tirupati developer in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800010205. It was launched in August 2017. It has 58 units in 1 building: 57 homes (1 and 2 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in February 2023, after an extension of 4 years 6 months from the original August 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 13% complete, final finishes 30% complete.
41 units booked out of total 58 units (71%).