Garuda Shatrunjay, Borivali West
Lapsed
by Messers Shree Umiya Builders & Developers · Borivali West, Mumbai 400092 · Map
- Launched
- Aug 20177 yrs 4 mths originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 1 yr 6 mthsWhat does Lapsed mean?
- Concrete structure
- 64%Mid-construction
- Booked
- 33 of 18018%
- Buildings
- 31.1 acres
- MahaRERA complaints
- 21Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 90
- 3 BHK
- 89
- Other units
- 1
- Total units
- 180
- Buildings
- 3
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 21
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 67% | 64% | 33% | 33 | |
| 67% | 41% | 33% | 33 | |
| 67% | 41% | 33% | 33 | |
| 67% | 37% | 33% | 33 |
"–" means MahaRERA shows no figure for that update.
About this project
Garuda Shatrunjay by Messers Shree Umiya Builders & Developers is a 180-unit SRA-sanctioned project in Borivali West, Mumbai 400092, launched in August 2017; its MahaRERA registration has lapsed. 33 units booked out of total 180 units. The concrete structure (RCC) is 64% complete.
Read full summary
Garuda Shatrunjay is an SRA-sanctioned project by Messers Shree Umiya Builders & Developers in Borivali West, Mumbai 400092, registered with MahaRERA as P51800011329. It was launched in August 2017. It has 180 units in 3 buildings: 179 homes (2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026, after an extension of 1 year 6 months from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation 67% complete, structure (RCC) 64% complete, final finishes 33% complete.
33 units booked out of total 180 units (18%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 41% to 64%.