Garuda Shatrunjay, Borivali West

Lapsed

by Messers Shree Umiya Builders & Developers · Borivali West, Mumbai 400092 · Map

Launched
Aug 20177 yrs 4 mths originally promised
Possession (MahaRERA)
Jun 2026Extended by 1 yr 6 mthsWhat does Lapsed mean?
Concrete structure
64%Mid-construction
Booked
33 of 18018%
Buildings
31.1 acres
MahaRERA complaints
21Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
90
3 BHK
89
Other units
1
Total units
180
Buildings
3
Land
1.1 acres
Phases
1
MahaRERA complaints
21

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation67%
Concrete structure (slabs)64%
Finishes, lifts and services33%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 67%Dec 2025: Excavation 67%Jul 2026: Excavation 67%Oct 2026: Excavation 67%Dec 2024: Concrete structure (RCC) 37%Dec 2025: Concrete structure (RCC) 41%Jul 2026: Concrete structure (RCC) 41%Oct 2026: Concrete structure (RCC) 64%Dec 2024: Final finishes 33%Dec 2025: Final finishes 33%Jul 2026: Final finishes 33%Oct 2026: Final finishes 33%Excavation 67%Concrete structure (RCC) 64%Final finishes 33%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
67%64%33%33
67%41%33%33
67%41%33%33
67%37%33%33

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Garuda Shatrunjay by Messers Shree Umiya Builders & Developers is a 180-unit SRA-sanctioned project in Borivali West, Mumbai 400092, launched in August 2017; its MahaRERA registration has lapsed. 33 units booked out of total 180 units. The concrete structure (RCC) is 64% complete.

Read full summary

Garuda Shatrunjay is an SRA-sanctioned project by Messers Shree Umiya Builders & Developers in Borivali West, Mumbai 400092, registered with MahaRERA as P51800011329. It was launched in August 2017. It has 180 units in 3 buildings: 179 homes (2 and 3 BHK) and 1 other unit (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2026, after an extension of 1 year 6 months from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation 67% complete, structure (RCC) 64% complete, final finishes 33% complete.

33 units booked out of total 180 units (18%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 41% to 64%.