Jai Shreeram Prasanna Chsl, Kurla West

Ready to moveLapsed

by Riyaz Ramzan Shah · Kurla West, Mumbai 400070 · Map

Launched
Aug 20174 yrs 10 mths originally promised
Possession (MahaRERA)
Aug 2026Extended by 4 yrs 2 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked (free sale)
17 of 17100% · 9 rehab units
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale17 booked out of 17 units

Rehab9 units for existing members

Total 26 units. Rehab units are not for sale.

Project facts

1 BHK
12
2 BHK
12
Other units
2
Total units
26
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1
Free-sale units
17
Rehab units
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services99%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 99%Jul 2026: Final finishes 99%Oct 2026: Final finishes 99%Excavation 100%Concrete structure (RCC) 100%Final finishes 99%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%99%17
100%100%99%17
100%100%99%17
100%100%0%18

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Jai Shreeram Prasanna Chsl by Riyaz Ramzan Shah is a 26-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in August 2017; its MahaRERA registration has lapsed. 17 units booked out of 17 units for sale. The concrete structure (RCC) is complete.

Read full summary

Jai Shreeram Prasanna Chsl is a BMC-sanctioned project by Riyaz Ramzan Shah in Kurla West, Mumbai 400070, registered with MahaRERA as P51800011427. It was launched in August 2017. It has 26 units in 1 building: 24 homes (1 and 2 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 26 units, 17 are for sale and 9 are rehab units for existing members.

Possession was due in August 2026, after an extension of 4 years 2 months from the original June 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 99% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

17 units booked out of 17 units for sale (100%).