Nirlon Employees Cooperative Housing Society Limited Building No 11, 12 ,13, Goregaon West
Lapsed
by Shivam Parivar Developers Pvt Ltd · Goregaon West, Mumbai 400062 · Map
- Launched
- Aug 20177 yrs 4 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 62%Mid-construction
- Booked (free sale)
- 305 of 32793% · 94 rehab units
- Buildings
- 10.6 acres
- MahaRERA complaints
- 16Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale305 booked out of 327 units
Rehab94 units for existing members
Total 421 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 200
- 2 BHK
- 190
- Other units
- 31
- Total units
- 421
- Buildings
- 1
- Land
- 0.6 acres
- Phases
- 1
- MahaRERA complaints
- 16
- Free-sale units
- 327
- Rehab units
- 94
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 62% | 2% | 305 | |
| 100% | 62% | 2% | 305 | |
| 100% | 62% | 2% | 305 | |
| 100% | 100% | 0% | 248 |
"–" means MahaRERA shows no figure for that update.
About this project
Nirlon Employees Cooperative Housing Society Limited Building No 11, 12,13 by Shivam Parivar Developers Pvt Ltd is a 421-unit MHADA-sanctioned project in Goregaon West, Mumbai 400062, launched in August 2017; its MahaRERA registration has lapsed. 305 units booked out of 327 units for sale. The concrete structure (RCC) is 62% complete.
Read full summary
Nirlon Employees Cooperative Housing Society Limited Building No 11, 12,13 is a MHADA-sanctioned project by Shivam Parivar Developers Pvt Ltd in Goregaon West, Mumbai 400062, registered with MahaRERA as P51800011447. It was launched in August 2017. It has 421 units in 1 building: 390 homes (1 and 2 BHK) and 31 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 421 units, 327 are for sale and 94 are rehab units for existing members.
Possession was due in December 2025, after an extension of 1 year from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 62% complete, final finishes 2% complete.
305 units booked out of 327 units for sale (93%).