Tridev Anubhav, Mulund West

by Tridev Realty And Construction Pvt Ltd · Mulund West, Mumbai 400080 · Map

Launched
Aug 20176 yrs 4 mths originally promised
Possession (MahaRERA)
Dec 2026Extended by 3 yrs
Concrete structure
100%Nearing possession
Booked (free sale)
47 of 47100% · 40 rehab units
Buildings
10.5 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Units booked

Free sale47 booked out of 47 units

Rehab40 units for existing members

Total 87 units. Rehab units are not for sale.

Project facts

1 BHK
2
2 BHK
47
3 BHK
35
Other units
3
Total units
87
Buildings
1
Land
0.5 acres
Phases
1
MahaRERA complaints
0
Free-sale units
47
Rehab units
40

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services81%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 24%Dec 2025: Final finishes 63%Jul 2026: Final finishes 81%Oct 2026: Final finishes 81%Excavation 100%Concrete structure (RCC) 100%Final finishes 81%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%81%47
100%100%81%47
100%100%63%47
100%100%24%40

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 40–200 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)6 yrs 4 mths4 yrs
Possession date extendedBy 3 yrs5 of 6
Possession date (MahaRERA)Dec 2026May 2022
Concrete structure (RCC)100%99%
Units booked (free sale)100%92%
MahaRERA complaints (filed by or against the builder)00

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Tridev Anubhav by Tridev Realty And Construction Pvt Ltd is an 87-unit SRA-sanctioned project in Mulund West, Mumbai 400080, launched in August 2017 with possession due in December 2026. 47 units booked out of 47 units for sale. The concrete structure (RCC) is complete.

Read full summary

Tridev Anubhav is an SRA-sanctioned project by Tridev Realty And Construction Pvt Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800011760. It was launched in August 2017. It has 87 units in 1 building: 84 homes (1, 2 and 3 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 87 units, 47 are for sale and 40 are rehab units for existing members.

Its registered possession date is December 2026, extended by 3 years from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes 81% complete.

47 units booked out of 47 units for sale (100%).