Marigold Miraaya, Mulund West

Ready to moveLapsed

by Marigold Realty · Mulund West, Mumbai 400080 · Map

Launched
Aug 20177 yrs 4 mths originally promised
Possession (MahaRERA)
Jun 2025Extended by 6 mthsWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
50 of 13338% · 44 in Jul 2026
Buildings
21 acre
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
114
3 BHK
19
Total units
133
Buildings
2
Land
1 acre
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services100%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 100%Excavation 100%Concrete structure (RCC) 100%Final finishes 100%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%100%50
100%100%0%44
100%100%0%44
100%100%0%43

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 6 similar projects in PIN 400080

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 6 similar projects in PIN 400080
MeasureThis projectSimilar projects
Launch to possession (as first promised)7 yrs 4 mths4 yrs 8 mths
Possession date extendedBy 6 mths6 of 6
Possession date (MahaRERA)Jun 2025Sep 2025
Concrete structure (RCC)100%92%
Units booked38%96%
MahaRERA complaints (filed by or against the builder)04

The 6 projects

Other phases of this project are not included in the similar projects.

About this project

Marigold Miraaya by Marigold Realty is a 133-unit BMC-sanctioned project in Mulund West, Mumbai 400080, launched in August 2017; its MahaRERA registration has lapsed. 50 units booked out of total 133 units. The concrete structure (RCC) is complete.

Read full summary

Marigold Miraaya is a BMC-sanctioned project by Marigold Realty in Mulund West, Mumbai 400080, registered with MahaRERA as P51800003669. It was launched in August 2017. It has 133 units in 2 buildings, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2025, after an extension of 6 months from the original December 2024. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes complete. Construction is reported as complete, but completion has not yet been recorded on MahaRERA.

50 units booked out of total 133 units (38%). Since the July 2026 update, 6 more units have been booked.