- Launched
- Sep 20172 yrs 3 mths originally promised
- Possession (MahaRERA)
- Jun 2024Extended by 4 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 50%Mid-construction
- Booked
- –
- Buildings
- 10.2 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 5
- 2 BHK
- 9
- 3 BHK
- 1
- Other units
- 5
- Total units
- 20
- Buildings
- 1
- Land
- 0.2 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 50% | 0% | – | |
| 100% | 50% | 0% | – | |
| 100% | 50% | 0% | 15 |
"–" means MahaRERA shows no figure for that update.
About this project
Saptashringi by Siroya Developers Pvt Ltd is a 20-unit project in Chembur, Mumbai 400089, launched in September 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 50% complete.
Read full summary
Saptashringi is a project by Siroya Developers Pvt Ltd in Chembur, Mumbai 400089, registered with MahaRERA as P51800012064. It was launched in September 2017. It has 20 units in 1 building: 15 homes (1, 2 and 3 BHK) and 5 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2024, after an extension of 4 years 6 months from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 50% complete, final finishes not started.