- Launched
- Sep 20176 yrs 3 mths originally promised
- Possession (MahaRERA)
- Oct 2026Extended by 2 yrs 10 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 62 of 10758%
- Buildings
- 11.1 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 84
- 2 BHK
- 23
- Total units
- 107
- Buildings
- 1
- Land
- 1.1 acres
- Phases
- 1
- MahaRERA complaints
- 2
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 0% | 62 | |
| 100% | 100% | 0% | 62 | |
| 100% | 75% | 0% | 62 | |
| 100% | 25% | 0% | 74 |
"–" means MahaRERA shows no figure for that update.
About this project
Aspire by M/s Radheshyam Developers is a 107-unit SRA-sanctioned project in Kandivali East, Mumbai 400101, launched in September 2017; its MahaRERA registration has lapsed. 62 units booked out of total 107 units. The concrete structure (RCC) is complete.
Read full summary
Aspire is an SRA-sanctioned project by M/s Radheshyam Developers in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800012142. It was launched in September 2017. It has 107 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Its registered possession date is October 2026, extended by 2 years 10 months from the original December 2023. Construction: excavation complete, structure (RCC) complete, final finishes not started.
62 units booked out of total 107 units (58%).