- Launched
- Sep 20176 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2025Extended by 2 yrsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked (free sale)
- 93 of 12972% · 84 rehab units
- Buildings
- 40.9 acres
- MahaRERA complaints
- 5Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale93 booked out of 129 units
Rehab84 units for existing members
Total 213 units. Rehab units are not for sale.
Project facts
- 1 BHK
- 66
- 2 BHK
- 137
- Other units
- 10
- Total units
- 213
- Buildings
- 4
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 5
- Free-sale units
- 129
- Rehab units
- 84
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 85% | 93 | |
| 25% | 25% | 21% | 93 | |
| 25% | 25% | 21% | 93 | |
| 100% | 100% | 85% | 0 |
"–" means MahaRERA shows no figure for that update.
About this project
Aerovista by Gagangiri Construction is a 213-unit MHADA-sanctioned project in Andheri East, Mumbai 400069, launched in September 2017; its MahaRERA registration has lapsed. 93 units booked out of 129 units for sale. The concrete structure (RCC) is complete.
Read full summary
Aerovista is a MHADA-sanctioned project by Gagangiri Construction in Andheri East, Mumbai 400069, registered with MahaRERA as P51800012150. It was launched in September 2017. It has 213 units in 4 buildings: 203 homes (1 and 2 BHK) and 10 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed. Of the 213 units, 129 are for sale and 84 are rehab units for existing members.
Possession was due in December 2025, after an extension of 2 years from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 85% complete.
93 units booked out of 129 units for sale (72%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 25% to 100% and the possession date has moved from December 2024 to December 2025.