- Launched
- Sep 20174 yrs 3 mths promised
- Possession (MahaRERA)
- Dec 2021Not extendedWhat does Lapsed mean?
- Concrete structure
- 67%Mid-construction
- Booked
- –
- Buildings
- 34.7 acres
- MahaRERA complaints
- 24Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 116
- 2 BHK
- 345
- Total units
- 461
- Buildings
- 3
- Land
- 4.7 acres
- Phases
- 1
- MahaRERA complaints
- 24
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 94% | 67% | 60% | – | |
| 94% | 67% | 60% | – | |
| 94% | 67% | 60% | 154 |
"–" means MahaRERA shows no figure for that update.
About this project
Centrio-By Mj Shah by Lakadawala Developers Pvt Ltd is a 461-unit project in Govandi, Mumbai 400043, launched in September 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 67% complete.
Read full summary
Centrio-By Mj Shah is a project by Lakadawala Developers Pvt Ltd in Govandi, Mumbai 400043, registered with MahaRERA as P51800012170. It was launched in September 2017. It has 461 units in 3 buildings, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2021. That date has passed and no extension has been recorded. Construction: excavation 94% complete, structure (RCC) 67% complete, final finishes 60% complete.
Lakadawala's track record in Mumbai
MahaRERA projects registered 2017–2024 in Mumbai
| Projects registered with MahaRERA | 5 |
|---|---|
| Total units across these projects | 1,184 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 0 |
| Lapsed | 1 |
| Under construction | 3 |
| Possession date extended on the builder's application | 1 |
| MahaRERA complaints (filed by or against the builder), all Lakadawala projects | 27 (4 of 5 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.