Jawahar Milan CHS, Malad East

Lapsed

by Landmark Corporation Pvt Ltd · Malad East, Mumbai 400097 · Map

Launched
Sep 20171 yr 3 mths originally promised
Possession (MahaRERA)
Dec 2019Extended by 1 yrWhat does Lapsed mean?
Concrete structure
6%Mid-construction
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
30
Total units
30
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation95%
Concrete structure (slabs)6%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 95%Dec 2025: Excavation 95%Jul 2026: Excavation 95%Dec 2024: Concrete structure (RCC) 6%Dec 2025: Concrete structure (RCC) 6%Jul 2026: Concrete structure (RCC) 6%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 95%Concrete structure (RCC) 6%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
95%6%0%–
95%6%0%–
95%6%0%15

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Jawahar Milan CHS by Landmark Corporation Pvt Ltd is a 30-unit project in Malad East, Mumbai 400097, launched in September 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 6% complete.

Read full summary

Jawahar Milan CHS is a project by Landmark Corporation Pvt Ltd in Malad East, Mumbai 400097, registered with MahaRERA as P51800012279. It was launched in September 2017. It has 30 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2019, after an extension of 1 year from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation 95% complete, structure (RCC) 6% complete, final finishes not started.