Manraj Enclave, Kurla West

Lapsed

by Rajan Lilaram Nathani Huf · Kurla West, Mumbai 400070 · Map

Launched
Sep 20172 yrs 3 mths originally promised
Possession (MahaRERA)
Dec 2020Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
–
Buildings
10.2 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
33
Total units
33
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services25%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 25%Dec 2025: Final finishes 25%Jul 2026: Final finishes 25%Excavation 100%Concrete structure (RCC) 100%Final finishes 25%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%25%–
100%100%25%–
100%100%25%26

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Manraj Enclave by Rajan Lilaram Nathani Huf is a 33-unit project in Kurla West, Mumbai 400070, launched in September 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Manraj Enclave is a project by Rajan Lilaram Nathani Huf in Kurla West, Mumbai 400070, registered with MahaRERA as P51800012287. It was launched in September 2017. It has 33 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2020, after an extension of 1 year from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 25% complete.