Tulsi Chambers, Chembur
Ready to moveLapsed
by Surana Construction (Chembur ) · Chembur, Mumbai 400071 · Map
- Launched
- Sep 20173 yrs 9 mths originally promised
- Possession (MahaRERA)
- Oct 2026Extended by 5 yrs 4 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 127 of 13296% · 124 in Jul 2026
- Buildings
- 11 acre
- MahaRERA complaints
- 14Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 132
- Total units
- 132
- Buildings
- 1
- Land
- 1 acre
- Phases
- 1
- MahaRERA complaints
- 14
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 127 | |
| 100% | 100% | 90% | 124 | |
| 100% | 95% | 50% | 122 | |
| 100% | 95% | 20% | 98 |
"–" means MahaRERA shows no figure for that update.
About this project
Tulsi Chambers by Surana Construction (Chembur) is a 132-unit SRA-sanctioned project in Chembur, Mumbai 400071, launched in September 2017; its MahaRERA registration has lapsed. 127 units booked out of total 132 units. The concrete structure (RCC) is complete.
Read full summary
Tulsi Chambers is an SRA-sanctioned project by Surana Construction (Chembur) in Chembur, Mumbai 400071, registered with MahaRERA as P51800012437. It was launched in September 2017. It has 132 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.
Its registered possession date is October 2026, extended by 5 years 4 months from the original June 2021. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
127 units booked out of total 132 units (96%). Since the July 2026 update, 3 more units have been booked and the possession date has moved from June 2022 to October 2026.