- Launched
- Sep 20174 yrs 3 mths originally promised
- Possession (MahaRERA)
- Dec 2022Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 51%Mid-construction
- Booked
- 8 of 3523%
- Buildings
- 10.8 acres
- MahaRERA complaints
- 1Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 35
- Total units
- 35
- Buildings
- 1
- Land
- 0.8 acres
- Phases
- 1
- MahaRERA complaints
- 1
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 51% | 0% | 8 | |
| 100% | 51% | 0% | – | |
| 100% | 51% | 0% | – | |
| 100% | 51% | 0% | 8 |
"–" means MahaRERA shows no figure for that update.
About this project
Palai Avenue by Dhanji Gelabhai Gala is a 35-unit project in Sion, Mumbai 400022, launched in September 2017; its MahaRERA registration has lapsed. 8 units booked out of total 35 units. The concrete structure (RCC) is 51% complete.
Read full summary
Palai Avenue is a project by Dhanji Gelabhai Gala in Sion, Mumbai 400022, registered with MahaRERA as P51800012468. It was launched in September 2017. It has 35 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2022, after an extension of 1 year from the original December 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 51% complete, final finishes not started.
8 units booked out of total 35 units (23%).