Skip to main content

Palai Avenue, Sion

Lapsed

by Dhanji Gelabhai Gala · Sion, Mumbai 400022 · Map

Launched
Sep 20174 yrs 3 mths originally promised
Possession (MahaRERA)
Dec 2022Extended by 1 yrWhat does Lapsed mean?
Concrete structure
51%Mid-construction
Booked
8 of 3523%
Buildings
10.8 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
35
Total units
35
Buildings
1
Land
0.8 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)51%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 51%Dec 2025: Concrete structure (RCC) 51%Jul 2026: Concrete structure (RCC) 51%Oct 2026: Concrete structure (RCC) 51%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 51%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%51%0%8
100%51%0%–
100%51%0%–
100%51%0%8

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Palai Avenue by Dhanji Gelabhai Gala is a 35-unit project in Sion, Mumbai 400022, launched in September 2017; its MahaRERA registration has lapsed. 8 units booked out of total 35 units. The concrete structure (RCC) is 51% complete.

Read full summary

Palai Avenue is a project by Dhanji Gelabhai Gala in Sion, Mumbai 400022, registered with MahaRERA as P51800012468. It was launched in September 2017. It has 35 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2022, after an extension of 1 year from the original December 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 51% complete, final finishes not started.

8 units booked out of total 35 units (23%).