Nirmal Lifestyle, Triumph And Thrill, Mulund West

Lapsed

by Nirmal Lifestyle Ltd · Mulund West, Mumbai 400080 · Map

Launched
Sep 20172 yrs 3 mths originally promised
Possession (MahaRERA)
Dec 2025Extended by 6 yrsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
268 of 27299%
Buildings
10.2 acres
MahaRERA complaints
8Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
272
Total units
272
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services18%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 18%Dec 2025: Final finishes 18%Jul 2026: Final finishes 18%Oct 2026: Final finishes 18%Excavation 100%Concrete structure (RCC) 100%Final finishes 18%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%18%268
100%100%18%–
100%100%18%–
100%100%18%268

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Nirmal Lifestyle, Triumph And Thrill by Nirmal Lifestyle Ltd is a 272-unit project in Mulund West, Mumbai 400080, launched in September 2017; its MahaRERA registration has lapsed. 268 units booked out of total 272 units. The concrete structure (RCC) is complete.

Read full summary

Nirmal Lifestyle, Triumph And Thrill is a project by Nirmal Lifestyle Ltd in Mulund West, Mumbai 400080, registered with MahaRERA as P51800012493. It was launched in September 2017. It has 272 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2025, after an extension of 6 years from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 18% complete.

268 units booked out of total 272 units (99%).