Sector R 3 Mhada, Goregaon East

Lapsed

by Guruashish Construction Private Limited · Goregaon East, Mumbai 400063 · Map

Launched
Sep 20173 mths promised
Possession (MahaRERA)
Dec 2017Not extendedWhat does Lapsed mean?
Concrete structure
75%Mid-construction
Booked
–
Buildings
41.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
394
Total units
394
Buildings
4
Land
1.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)75%
Finishes, lifts and services64%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 75%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 75%Oct 2026: Concrete structure (RCC) 75%Dec 2024: Final finishes 64%Dec 2025: Final finishes 64%Jul 2026: Final finishes 64%Oct 2026: Final finishes 64%Excavation 100%Concrete structure (RCC) 75%Final finishes 64%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%75%64%–
100%75%64%–
100%75%64%–
100%75%64%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sector R 3 Mhada by Guruashish Construction Private Limited is a 394-unit project in Goregaon East, Mumbai 400063, launched in September 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 75% complete.

Read full summary

Sector R 3 Mhada is a project by Guruashish Construction Private Limited in Goregaon East, Mumbai 400063, registered with MahaRERA as P51800012580. It was launched in September 2017. It has 394 units in 4 buildings, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2017. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 75% complete, final finishes 64% complete.