Avis Residency, Ghatkopar East

Lapsed

by Avi housing Realtors · Ghatkopar East, Mumbai 400077 · Map

Launched
Sep 20172 yrs 3 mths originally promised
Possession (MahaRERA)
Aug 2022Extended by 2 yrs 8 mthsWhat does Lapsed mean?
Concrete structure
95%Mid-construction
Booked
–
Buildings
10.4 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
8
3 BHK
21
Other units
2
Total units
31
Buildings
1
Land
0.4 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)95%
Finishes, lifts and services75%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 95%Dec 2025: Concrete structure (RCC) 95%Jul 2026: Concrete structure (RCC) 95%Dec 2024: Final finishes 75%Dec 2025: Final finishes 75%Jul 2026: Final finishes 75%Excavation 100%Concrete structure (RCC) 95%Final finishes 75%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%95%75%–
100%95%75%–
100%95%75%27

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Avis Residency by Avi housing Realtors is a 31-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in September 2017; its MahaRERA registration has lapsed. The concrete structure (RCC) is 95% complete.

Read full summary

Avis Residency is a BMC-sanctioned project by Avi housing Realtors in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800012791. It was launched in September 2017. It has 31 units in 1 building: 29 homes (2 and 3 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in August 2022, after an extension of 2 years 8 months from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 95% complete, final finishes 75% complete.