Adora Enclave Residency / Commercial, Vikhroli

Ready to moveLapsed

by Hemant Vinaykant Parikh · Vikhroli, Mumbai 400083 · Map

Launched
Sep 20174 yrs 4 mths promised
Possession (MahaRERA)
Jan 2022Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
23 of 23100%
Buildings
10.1 acres
MahaRERA complaints
3Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
19
Other units
4
Total units
23
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
3

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%23
100%100%90%–
100%100%90%–
100%100%90%23

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Adora Enclave Residency / Commercial by Hemant Vinaykant Parikh is a 23-unit project in Vikhroli, Mumbai 400083, launched in September 2017; its MahaRERA registration has lapsed. 23 units booked out of total 23 units. The concrete structure (RCC) is complete.

Read full summary

Adora Enclave Residency / Commercial is a project by Hemant Vinaykant Parikh in Vikhroli, Mumbai 400083, registered with MahaRERA as P51800012841. It was launched in September 2017. It has 23 units in 1 building: 19 homes (1 BHK) and 4 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in January 2022. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

23 units booked out of total 23 units (100%).