Horizon, Bhandup West
by Ajanta Airavat Infrastructure Limited Liability Partnership · Bhandup West, Mumbai 400078 · Map
- Launched
- Sep 20173 yrs 3 mths originally promised
- Possession (MahaRERA)
- Sep 2029Extended by 8 yrs 9 mths
- Concrete structure
- 50%Mid-construction
- Booked
- 115 of 17167% · 113 in Jul 2026
- Buildings
- 41.3 acres
- MahaRERA complaints
- 10Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 43
- 2 BHK
- 126
- 3 BHK
- 2
- Total units
- 171
- Buildings
- 4
- Land
- 1.3 acres
- Phases
- 1
- MahaRERA complaints
- 10
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 75% | 50% | 50% | 115 | |
| 75% | 50% | 45% | 113 | |
| 75% | 50% | 0% | 111 | |
| 75% | 50% | 0% | 79 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400078
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 3 yrs 3 mths | 5 yrs 3 mths |
| Possession date extended | By 8 yrs 9 mths | 2 of 3 |
| Possession date (MahaRERA) | Sep 2029 | Jan 2027 |
| Concrete structure (RCC) | 50% | 83% |
| Units booked | 67% | 72% |
| MahaRERA complaints (filed by or against the builder) | 10 | 3 |
The 3 projects
- Daffodil Heights, Bhandup West
- Vastukalp, Bhandup West
- Primo, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Daffodil Heights | September 2017 | April 2030 | 83% | 137 units booked out of 186 units for sale |
| Vastukalp | August 2017 | December 2025 | 10% | 89 units booked out of total 238 units |
| Primo | July 2017 | January 2027 | 100% | 89 units booked out of total 123 units |
About this project
Horizon by Ajanta Airavat Infrastructure Limited Liability Partnership is a 171-unit BMC-sanctioned project in Bhandup West, Mumbai 400078, launched in September 2017 with possession due in September 2029. 115 units booked out of total 171 units. The concrete structure (RCC) is 50% complete.
Read full summary
Horizon is a BMC-sanctioned project by Ajanta Airavat Infrastructure Limited Liability Partnership in Bhandup West, Mumbai 400078, registered with MahaRERA as P51800013296. It was launched in September 2017. It has 171 units in 4 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is September 2029, extended by 8 years 9 months from the original December 2020. Construction: excavation 75% complete, structure (RCC) 50% complete, final finishes 50% complete.
115 units booked out of total 171 units (67%). Since the July 2026 update, 2 more units have been booked and the possession date has moved from May 2023 to September 2029.