Daffodil Heights, Bhandup West
by Shree Krishna Constructions · Bhandup West, Mumbai 400078 · Map
- Launched
- Sep 20175 yrs 3 mths originally promised
- Possession (MahaRERA)
- Apr 2030Extended by 7 yrs 4 mths
- Concrete structure
- 83%Mid-construction
- Booked (free sale)
- 137 of 18674% · 140 rehab units
- Buildings
- 40.5 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Units booked
Free sale137 booked out of 186 units
Rehab140 units for existing members
Total 326 units. Rehab units are not for sale.
Project facts
- 1 RK
- 28
- 1 BHK
- 251
- 2 BHK
- 41
- Other units
- 6
- Total units
- 326
- Buildings
- 4
- Land
- 0.5 acres
- Phases
- 1
- MahaRERA complaints
- 3
- Free-sale units
- 186
- Rehab units
- 140
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 83% | 75% | 137 | |
| 100% | 83% | 75% | 129 | |
| 75% | 75% | 74% | 115 | |
| 75% | 75% | 62% | 0 |
"–" means MahaRERA shows no figure for that update.
Compared with 5 similar projects in PIN 400078
Projects with 150–700 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 5 yrs 3 mths | 5 yrs 5 mths |
| Possession date extended | By 7 yrs 4 mths | 4 of 5 |
| Possession date (MahaRERA) | Apr 2030 | Jun 2027 |
| Concrete structure (RCC) | 83% | 100% |
| Units booked (free sale) | 74% | 89% |
| MahaRERA complaints (filed by or against the builder) | 3 | 0 |
The 5 projects
- Horizon, Bhandup West
- Vaikunth Dham CHS Ltd, Bhandup West
- Platinum Heights, Bhandup West
- Shraddha Evoque, Bhandup West
- Avante, Bhandup West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Horizon | September 2017 | September 2029 | 50% | 115 units booked out of total 171 units |
| Vaikunth Dham CHS Ltd | August 2017 | December 2022 | 100% | – |
| Platinum Heights | August 2017 | June 2027 | 100% | 224 units booked out of 263 units for sale |
| Shraddha Evoque | August 2017 | August 2026 | 100% | 569 units booked out of 612 units for sale |
| Avante | July 2017 | April 2028 | 100% | 378 units booked out of total 383 units |
About this project
Daffodil Heights by Shree Krishna Constructions is a 326-unit SRA-sanctioned project in Bhandup West, Mumbai 400078, launched in September 2017 with possession due in April 2030. 137 units booked out of 186 units for sale. The concrete structure (RCC) is 83% complete.
Read full summary
Daffodil Heights is an SRA-sanctioned project by Shree Krishna Constructions in Bhandup West, Mumbai 400078, registered with MahaRERA as P51900013369. It was launched in September 2017. It has 326 units in 4 buildings: 320 homes (1 RK, 1 BHK and 2 BHK) and 6 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active. Of the 326 units, 186 are for sale and 140 are rehab units for existing members.
Its registered possession date is April 2030, extended by 7 years 4 months from the original December 2022. Construction: excavation complete, structure (RCC) 83% complete, final finishes 75% complete.
137 units booked out of 186 units for sale (74%). Since the July 2026 update, 8 more units have been booked and the possession date has moved from December 2023 to April 2030.