Sai Laxmi Chsl, Borivali West

Lapsed

by Shreejani Developers · Borivali West, Mumbai 400092 · Map

Launched
Sep 20173 mths originally promised
Possession (MahaRERA)
Dec 2018Extended by 1 yrWhat does Lapsed mean?
Concrete structure
0%Early stage
Booked
3 of 1225%
Buildings
10.1 acres
MahaRERA complaints
5Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
12
Total units
12
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
5

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)0%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 0%Dec 2025: Concrete structure (RCC) 0%Jul 2026: Concrete structure (RCC) 0%Oct 2026: Concrete structure (RCC) 0%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Final finishes 90%Concrete structure (RCC) 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%0%90%3
100%0%90%–
100%0%90%–
100%0%90%3

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sai Laxmi Chsl by Shreejani Developers is a 12-unit project in Borivali West, Mumbai 400092, launched in September 2017; its MahaRERA registration has lapsed. 3 units booked out of total 12 units. Work on the concrete structure (RCC) has not started.

Read full summary

Sai Laxmi Chsl is a project by Shreejani Developers in Borivali West, Mumbai 400092, registered with MahaRERA as P51800013373. It was launched in September 2017. It has 12 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2018, after an extension of 1 year from the original December 2017. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) not started, final finishes 90% complete.

3 units booked out of total 12 units (25%).