Ajmera Iconic, Kandivali East

by M K Group · Kandivali East, Mumbai 400101 · Map

Launched
Oct 201714 yrs 2 mths originally promised
Possession (MahaRERA)
Apr 2032Extended by 4 mths
Concrete structure
45%Mid-construction
Booked
32 of 9833% · 13 in Dec 2024
Buildings
10.2 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
33
3 BHK
32
4 BHK
33
Total units
98
Buildings
1
Land
0.2 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation80%
Concrete structure (slabs)45%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Oct 2026Dec 2024: Excavation 80%Oct 2026: Excavation 80%Dec 2024: Concrete structure (RCC) 25%Oct 2026: Concrete structure (RCC) 45%Dec 2024: Final finishes 0%Oct 2026: Final finishes 0%Excavation 80%Concrete structure (RCC) 45%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
80%45%0%32
80%25%0%13

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Ajmera Iconic by M K Group (Ajmera) is a 98-unit SRA-sanctioned project in Kandivali East, Mumbai 400101, launched in October 2017 with possession due in April 2032. 32 units booked out of total 98 units. The concrete structure (RCC) is 45% complete.

Read full summary

Ajmera Iconic is an SRA-sanctioned project by M K Group in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800013436. It was launched in October 2017. It has 98 units in 1 building, with 2, 3 and 4 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is April 2032, extended by 4 months from the original December 2031. Construction: excavation 80% complete, structure (RCC) 45% complete, final finishes not started.

32 units booked out of total 98 units (33%). Since the December 2024 update, 19 more units have been booked, the reported concrete structure (RCC) has gone from 25% to 45% and the possession date has moved from December 2031 to April 2032.

Ajmera's track record in Mumbai

MahaRERA projects registered 2017–2026 in Mumbai

Projects registered with MahaRERA23
Total units across these projects4,563
Completed without extending the possession date10
Completed after an extension0
Lapsed3
Under construction10
Possession date extended on the builder's application2
Typical time from launch to 100% structure4 years 11 months
MahaRERA complaints (filed by or against the builder), all Ajmera projects15 (9 of 23 projects)

See all Ajmera projects →