Ajmera projects in Mumbai

MahaRERA projects by Ajmera registered 2017–2026 in Mumbai.

Projects registered with MahaRERA23
Total units across these projects4,563
Full record

MahaRERA projects registered 2017–2026 in Mumbai

Completed without extending the possession date10
Completed after an extension0
Lapsed3
Under construction10
Possession date extended on the builder's application2
Typical time from launch to 100% structure4 years 11 months
MahaRERA complaints (filed by or against the builder), all Ajmera projects15 (9 of 23 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Wadala East (5) · Malad West (3) · Kalbadevi (2) · Kandivali East (1) · Ghatkopar West (1) · Borivali West (1) · Juhu (1) · Ghatkopar East (1) · Vile Parle West (1) · Prabhadevi (1)

Under construction

ProjectVillageStagePossessionBooked
33FifteenBandra WestEarly stageMay 202926 units booked out of 78 units for sale
Ajmera ArhamMalad WestMid-constructionJuly 2027166 units booked out of total 209 units
Ajmera DowntownKalbadeviNearing possessionDecember 202773 units booked out of total 254 units
Ajmera Greenfinity · 2 phasesWadala EastReady to moveJun 2025 – May 2027–
Ajmera IconicKandivali EastMid-constructionApril 203232 units booked out of total 98 units
Ajmera Manhattan · 2 phasesWadala EastMid-constructionJun 2027 – Jul 2030798 units booked out of total 983 units
Ajmera SolisVikhroliEarly stageJanuary 2031356 units booked out of total 429 units
Building No 2 Ajmera ShikharMalad WestEarly stageDecember 203010 units booked out of 161 units for sale
Vann By AjmeraAndheri WestEarly stageJanuary 20312 units booked out of 29 units for sale
Completed
ProjectVillageStatus
Ajmera BoulevardMalad WestCompleted
Ajmera ClassiquePrabhadeviCompleted
Ajmera EdenGhatkopar EastCompleted
Ajmera ManorBorivali WestCompleted
Ajmera MidtownKalbadeviCompleted
Ajmera PriveJuhuCompleted
Ajmera SereneDadar EastCompleted
Ajmera ShringaarVile Parle WestCompleted
Ajmera SikovaGhatkopar WestCompleted
Ajmera ZeonWadala EastCompleted
Lapsed
ProjectVillageStatus
Ajmera AeonWadala EastLapsed
Ajmera TreonWadala EastLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.