Ruparel Optima Ph I, Kandivali West
by Ruparel Infra & Realty Pvt Ltd · Kandivali West, Mumbai 400067 · Map
- Launched
- Oct 20175 yrs 2 mths originally promised
- Possession (MahaRERA)
- Apr 2027Extended by 4 yrs 4 mths
- Concrete structure
- 95%Mid-construction
- Booked
- 1,464 of 1,53595%
- Buildings
- 36.3 acres
- MahaRERA complaints
- 284Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 1,505
- Other units
- 30
- Total units
- 1,535
- Buildings
- 3
- Land
- 6.3 acres
- Phases
- 1
- MahaRERA complaints
- 284
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 97% | 95% | 0% | 1,464 | |
| 0% | 0% | 0% | 1,464 | |
| 0% | 0% | 0% | 1,464 | |
| 0% | 0% | 0% | 1,508 |
"–" means MahaRERA shows no figure for that update.
About this project
Ruparel Optima Ph I by Ruparel Infra & Realty Pvt Ltd is a 1,535-unit SRA-sanctioned project in Kandivali West, Mumbai 400067, launched in October 2017 with possession due in April 2027. 1,464 units booked out of total 1,535 units. The concrete structure (RCC) is 95% complete.
Read full summary
Ruparel Optima Ph I is an SRA-sanctioned project by Ruparel Infra & Realty Pvt Ltd in Kandivali West, Mumbai 400067, registered with MahaRERA as P51800013701. It was launched in October 2017. It has 1,535 units in 3 buildings: 1,505 homes (1 BHK) and 30 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Active.
Its registered possession date is April 2027, extended by 4 years 4 months from the original December 2022. Construction: excavation 97% complete, structure (RCC) 95% complete, final finishes not started.
1,464 units booked out of total 1,535 units (95%). Since the July 2026 update, the reported concrete structure (RCC) has gone from 0% to 95% and the possession date has moved from December 2025 to April 2027.
Ruparel's track record in Mumbai
MahaRERA projects registered 2017–2025 in Mumbai
| Projects registered with MahaRERA | 28 |
|---|---|
| Total units across these projects | 6,570 |
| Completed without extending the possession date | 0 |
| Completed after an extension | 1 |
| Lapsed | 12 |
| Under construction | 15 |
| Possession date extended on the builder's application | 14 |
| Typical time from launch to 100% structure | 5 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Ruparel projects | 872 (22 of 28 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.