Ruparel projects in Mumbai
MahaRERA projects by Ruparel registered 2017–2025 in Mumbai.
| Projects registered with MahaRERA | 28 |
|---|---|
| Total units across these projects | 6,570 |
Full record
MahaRERA projects registered 2017–2025 in Mumbai
| Completed without extending the possession date | 0 |
|---|---|
| Completed after an extension | 1 |
| Lapsed | 12 |
| Under construction | 15 |
| Possession date extended on the builder's application | 14 |
| Typical time from launch to 100% structure | 5 years 9 months |
| MahaRERA complaints (filed by or against the builder), all Ruparel projects | 872 (22 of 28 projects) |
What these mean
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.
Where they build: Kandivali West (5) · Kurla East (4) · Parel (3) · Chembur (2) · Mulund West (2) · Santacruz West (1) · Mulund East (1) · Malad West (1) · Ghatkopar East (1) · Borivali West (1)
Under construction
| Project | Village | Stage | Possession | Booked |
|---|---|---|---|---|
| Ruparel Arista | Mulund West | Mid-construction | March 2028 | 10 units booked out of 17 units for sale |
| Ruparel Celestia | Mulund East | Nearing possession | December 2026 | 56 units booked out of total 68 units |
| Ruparel Crest | Kurla East | Mid-construction | December 2026 | 230 units booked out of total 277 units |
| Ruparel House | Malabar Hill | Mid-construction | December 2027 | 8 units booked out of 11 units for sale |
| Ruparel Jewel | Parel | Mid-construction | April 2027 | 99 units booked out of total 191 units |
| Ruparel Optima Ph I | Kandivali West | Mid-construction | April 2027 | 1,464 units booked out of total 1,535 units |
| Ruparel Panache | Santacruz West | Ready to move | December 2026 | 138 units booked out of total 148 units |
| Ruparel Premia | Mulund West | Mid-construction | December 2027 | 83 units booked out of total 103 units |
| Ruparel Pristine | Ghatkopar East | Nearing possession | December 2026 | 60 units booked out of total 72 units |
| Ruparel Skygreens I | Kandivali West | Nearing possession | December 2026 | 405 units booked out of total 481 units |
| Ruparel Stardom | Malad West | Mid-construction | June 2028 | 412 units booked out of total 738 units |
| Ruparel Urbana | Kurla East | Mid-construction | December 2028 | 343 units booked out of total 490 units |
| Ruparel Vivanza | Byculla | Early stage | March 2027 | – |
| Ruparel Westsky | Kandivali West | Mid-construction | December 2027 | 220 units booked out of total 336 units |
| Ruparel Zinnia | Borivali West | Mid-construction | June 2028 | 108 units booked out of total 133 units |
Completed
| Project | Village | Status |
|---|---|---|
| Ruparel Elara | Kandivali West | Completed |
Lapsed
| Project | Village | Status |
|---|---|---|
| Ruparel Ariana | Sewri | Lapsed |
| Ruparel Iris | Mahim | Lapsed |
| Ruparel Livia | Kurla East | Lapsed |
| Ruparel Luminare | Dadar East | Lapsed |
| Ruparel Millennia | Parel | Lapsed |
| Ruparel NOVA | Parel | Lapsed |
| Ruparel Orion | Chembur | Lapsed |
| Ruparel Palacio Ph I | Kandivali West | Lapsed |
| Ruparel Pride | Kurla East | Lapsed |
| Ruparel Primero | Chembur | Lapsed |
| Ruparel Regalia | Sion | Lapsed |
| Shaanti Ashish | Dadar West | Lapsed |
Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.
Is a project grouped wrongly or a figure out of date? Tell us