Ruparel projects in Mumbai

MahaRERA projects by Ruparel registered 2017–2025 in Mumbai.

Projects registered with MahaRERA28
Total units across these projects6,570
Full record

MahaRERA projects registered 2017–2025 in Mumbai

Completed without extending the possession date0
Completed after an extension1
Lapsed12
Under construction15
Possession date extended on the builder's application14
Typical time from launch to 100% structure5 years 9 months
MahaRERA complaints (filed by or against the builder), all Ruparel projects872 (22 of 28 projects)
What these mean
  • Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
  • Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
  • Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
  • Under construction: MahaRERA status Active.
  • Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
  • Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
  • MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.

Where they build: Kandivali West (5) · Kurla East (4) · Parel (3) · Chembur (2) · Mulund West (2) · Santacruz West (1) · Mulund East (1) · Malad West (1) · Ghatkopar East (1) · Borivali West (1)

Under construction

ProjectVillageStagePossessionBooked
Ruparel AristaMulund WestMid-constructionMarch 202810 units booked out of 17 units for sale
Ruparel CelestiaMulund EastNearing possessionDecember 202656 units booked out of total 68 units
Ruparel CrestKurla EastMid-constructionDecember 2026230 units booked out of total 277 units
Ruparel HouseMalabar HillMid-constructionDecember 20278 units booked out of 11 units for sale
Ruparel JewelParelMid-constructionApril 202799 units booked out of total 191 units
Ruparel Optima Ph IKandivali WestMid-constructionApril 20271,464 units booked out of total 1,535 units
Ruparel PanacheSantacruz WestReady to moveDecember 2026138 units booked out of total 148 units
Ruparel PremiaMulund WestMid-constructionDecember 202783 units booked out of total 103 units
Ruparel PristineGhatkopar EastNearing possessionDecember 202660 units booked out of total 72 units
Ruparel Skygreens IKandivali WestNearing possessionDecember 2026405 units booked out of total 481 units
Ruparel StardomMalad WestMid-constructionJune 2028412 units booked out of total 738 units
Ruparel UrbanaKurla EastMid-constructionDecember 2028343 units booked out of total 490 units
Ruparel VivanzaBycullaEarly stageMarch 2027–
Ruparel WestskyKandivali WestMid-constructionDecember 2027220 units booked out of total 336 units
Ruparel ZinniaBorivali WestMid-constructionJune 2028108 units booked out of total 133 units
Completed
ProjectVillageStatus
Ruparel ElaraKandivali WestCompleted
Lapsed
ProjectVillageStatus
Ruparel ArianaSewriLapsed
Ruparel IrisMahimLapsed
Ruparel LiviaKurla EastLapsed
Ruparel LuminareDadar EastLapsed
Ruparel MillenniaParelLapsed
Ruparel NOVAParelLapsed
Ruparel OrionChemburLapsed
Ruparel Palacio Ph IKandivali WestLapsed
Ruparel PrideKurla EastLapsed
Ruparel PrimeroChemburLapsed
Ruparel RegaliaSionLapsed
Shaanti AshishDadar WestLapsed

Figures as reported to MahaRERA. Projects without a FlatNama page are older or outside the lists; they are named but not linked.