Tridhaatu Morya, Mankhurd
Lapsed
by Tridhaatu Morya Developers Pvt Ltd · Mankhurd, Mumbai 400088 · Map
- Launched
- Oct 2017First of 2 phases
- Possession (MahaRERA)
- Dec 2025Not extendedWhat does Lapsed mean?
- Concrete structure
- 75%Weighted across 2 phases
- Booked
- 144 of 21467%
- Buildings
- 30.6 acres
- MahaRERA complaints
- 2Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 35
- 2 BHK
- 178
- 3 BHK
- 1
- Total units
- 214
- Buildings
- 3
- Land
- 0.6 acres
- Phases
- 2
- MahaRERA complaints
- 2
The 2 phases
| Phase | MahaRERA no. | Flats | Possession | Structure | Booked |
|---|---|---|---|---|---|
| Tridhaatu Morya Ready to move Lapsed | P51800013775 | 106 | 100% | 90% | |
| Tridhaatu Morya II Mid-construction Lapsed | P51800015776 | 108 | 50% | 45% |
Show updates by phase
Tridhaatu Morya (P51800013775)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 95% | 95 | |
| 100% | 100% | 95% | 95 | |
| 100% | 100% | 95% | 83 |
"–" means MahaRERA shows no figure for that update.
Tridhaatu Morya II (P51800015776)
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 50% | 50% | 48% | 49 | |
| 50% | 50% | 48% | 49 | |
| 50% | 50% | 48% | 32 |
"–" means MahaRERA shows no figure for that update.
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
About this project
Tridhaatu Morya by Tridhaatu Morya Developers Pvt Ltd is a 214-unit BMC-sanctioned project in Mankhurd, Mumbai 400088, registered with MahaRERA in 2 phases, with possession due in December 2025. 144 units booked out of total 214 units. The concrete structure (RCC) is 75% complete.
Read full summary
Tridhaatu Morya is a BMC-sanctioned project by Tridhaatu Morya Developers Pvt Ltd in Mankhurd, Mumbai 400088, registered with MahaRERA as 2 phases (P51800013775, P51800015776). The first phase was launched in October 2017. Together the phases have 214 units in 3 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Both phases are lapsed on MahaRERA.
The registered possession date is December 2025; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 75% complete and final finishes 71% complete. Neither phase has its structure complete.
144 units booked out of total 214 units (67%).
Tridhaatu's track record in Mumbai
MahaRERA projects registered 2017–2023 in Mumbai
| Projects registered with MahaRERA | 12 |
|---|---|
| Total units across these projects | 649 |
| Completed without extending the possession date | 1 |
| Completed after an extension | 1 |
| Lapsed | 6 |
| Under construction | 4 |
| Possession date extended on the builder's application | 6 |
| Typical time from launch to 100% structure | 7 years 4 months |
| MahaRERA complaints (filed by or against the builder), all Tridhaatu projects | 33 (10 of 12 projects) |
- Completed without extending the possession date: MahaRERA shows the project Completed and the builder did not apply to extend its possession date. MahaRERA's blanket extensions (COVID 2020–21, and the automatic 4 months of August 2026) are not counted as the builder's.
- Completed after an extension: MahaRERA shows the project Completed after the builder extended its possession date.
- Lapsed: the possession date passed with no extension or completion filed on MahaRERA; it does not by itself mean work has stopped.
- Under construction: MahaRERA status Active.
- Possession date extended on the builder's application: counted across all of the above, so it overlaps them.
- Typical time from launch to 100% structure: the middle value for projects whose concrete structure (RCC) reached 100% between December 2023 and October 2026, counted from registration.
- MahaRERA complaints: complaints on MahaRERA filed by or against the builder, on all its projects.