Tridhaatu Morya, Mankhurd

Lapsed

by Tridhaatu Morya Developers Pvt Ltd · Mankhurd, Mumbai 400088 · Map

Launched
Oct 2017First of 2 phases
Possession (MahaRERA)
Dec 2025Not extendedWhat does Lapsed mean?
Concrete structure
75%Weighted across 2 phases
Booked
144 of 21467%
Buildings
30.6 acres
MahaRERA complaints
2Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
35
2 BHK
178
3 BHK
1
Total units
214
Buildings
3
Land
0.6 acres
Phases
2
MahaRERA complaints
2

The 2 phases

PhaseMahaRERA no.FlatsPossessionStructureBooked
Tridhaatu Morya
Ready to move Lapsed
P51800013775106100%90%
Tridhaatu Morya II
Mid-construction Lapsed
P5180001577610850%45%
Show updates by phase

Tridhaatu Morya (P51800013775)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%95
100%100%95%95
100%100%95%83

"–" means MahaRERA shows no figure for that update.

Tridhaatu Morya II (P51800015776)

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
50%50%48%49
50%50%48%49
50%50%48%32

"–" means MahaRERA shows no figure for that update.

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation75%
Concrete structure (slabs)75%
Finishes, lifts and services71%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 75%Dec 2025: Excavation 75%Jul 2026: Excavation 75%Dec 2024: Concrete structure (RCC) 75%Dec 2025: Concrete structure (RCC) 75%Jul 2026: Concrete structure (RCC) 75%Dec 2024: Final finishes 71%Dec 2025: Final finishes 71%Jul 2026: Final finishes 71%Excavation 75%Concrete structure (RCC) 75%Final finishes 71%

How to read construction stages

About this project

Tridhaatu Morya by Tridhaatu Morya Developers Pvt Ltd is a 214-unit BMC-sanctioned project in Mankhurd, Mumbai 400088, registered with MahaRERA in 2 phases, with possession due in December 2025. 144 units booked out of total 214 units. The concrete structure (RCC) is 75% complete.

Read full summary

Tridhaatu Morya is a BMC-sanctioned project by Tridhaatu Morya Developers Pvt Ltd in Mankhurd, Mumbai 400088, registered with MahaRERA as 2 phases (P51800013775, P51800015776). The first phase was launched in October 2017. Together the phases have 214 units in 3 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Both phases are lapsed on MahaRERA.

The registered possession date is December 2025; no phase has an extended possession date. Across all phases, weighted by flats, the concrete structure (RCC) is 75% complete and final finishes 71% complete. Neither phase has its structure complete.

144 units booked out of total 214 units (67%).

Tridhaatu's track record in Mumbai

MahaRERA projects registered 2017–2023 in Mumbai

Projects registered with MahaRERA12
Total units across these projects649
Completed without extending the possession date1
Completed after an extension1
Lapsed6
Under construction4
Possession date extended on the builder's application6
Typical time from launch to 100% structure7 years 4 months
MahaRERA complaints (filed by or against the builder), all Tridhaatu projects33 (10 of 12 projects)

See all Tridhaatu projects →