Fatima Arch And Developers, Kurla West
Lapsed
by Fatima Arch & Developers · Kurla West, Mumbai 400070 · Map
- Launched
- Oct 20171 yr 2 mths originally promised
- Possession (MahaRERA)
- Dec 2019Extended by 1 yrWhat does Lapsed mean?
- Concrete structure
- 80%Mid-construction
- Booked
- 14 of 2167%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 5Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- Other units
- 21
- Total units
- 21
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 5
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 0% | 14 | |
| 100% | 80% | 0% | – | |
| 100% | 80% | 0% | – | |
| 100% | 80% | 0% | 14 |
"–" means MahaRERA shows no figure for that update.
About this project
Fatima Arch And Developers by Fatima Arch & Developers is a 21-unit project in Kurla West, Mumbai 400070, launched in October 2017; its MahaRERA registration has lapsed. 14 units booked out of total 21 units. The concrete structure (RCC) is 80% complete.
Read full summary
Fatima Arch And Developers is a project by Fatima Arch & Developers in Kurla West, Mumbai 400070, registered with MahaRERA as P51800013857. It was launched in October 2017. It has 21 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2019, after an extension of 1 year from the original December 2018. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 80% complete, final finishes not started.
14 units booked out of total 21 units (67%).