- Launched
- Nov 20176 yrs 1 mth originally promised
- Possession (MahaRERA)
- Jun 2026Extended by 2 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Nearing possession
- Booked
- 653 of 67197% · 641 in Jul 2026
- Buildings
- 20.9 acres
- MahaRERA complaints
- 37Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 518
- 2 BHK
- 133
- Other units
- 20
- Total units
- 671
- Buildings
- 2
- Land
- 0.9 acres
- Phases
- 1
- MahaRERA complaints
- 37
- Reserved units
- 247
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 81% | 653 | |
| 100% | 100% | 79% | 641 | |
| 95% | 95% | 40% | – | |
| 85% | 85% | 48% | 382 |
"–" means MahaRERA shows no figure for that update.
About this project
Enso Sanza by Sai Aastha Developers is a 671-unit SRA-sanctioned project in Kandivali East, Mumbai 400101, launched in November 2017; its MahaRERA registration has lapsed. 653 units booked out of total 671 units. The concrete structure (RCC) is complete.
Read full summary
Enso Sanza is an SRA-sanctioned project by Sai Aastha Developers in Kandivali East, Mumbai 400101, registered with MahaRERA as P51800013955. It was launched in November 2017. It has 671 units in 2 buildings: 651 homes (1 and 2 BHK) and 20 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2026, after an extension of 2 years 6 months from the original December 2023. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 81% complete.
653 units booked out of total 671 units (97%). Since the July 2026 update, 12 more units have been booked and the possession date has moved from December 2024 to June 2026.