Sky Heights, Chandivali

Lapsed

by Skylink Developers · Chandivali, Mumbai 400072 · Map

Launched
Nov 20173 yrs 2 mths originally promised
Possession (MahaRERA)
Jul 2022Extended by 1 yr 6 mthsWhat does Lapsed mean?
Concrete structure
100%Nearing possession
Booked
100 of 100100%
Buildings
10.6 acres
MahaRERA complaints
9Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
50
2 BHK
50
Total units
100
Buildings
1
Land
0.6 acres
Phases
1
MahaRERA complaints
9

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services10%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 10%Dec 2025: Final finishes 10%Jul 2026: Final finishes 10%Oct 2026: Final finishes 10%Excavation 100%Concrete structure (RCC) 100%Final finishes 10%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%10%100
100%100%10%–
100%100%10%–
100%100%10%100

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Sky Heights by Skylink Developers is a 100-unit project in Chandivali, Mumbai 400072, launched in November 2017; its MahaRERA registration has lapsed. 100 units booked out of total 100 units. The concrete structure (RCC) is complete.

Read full summary

Sky Heights is a project by Skylink Developers in Chandivali, Mumbai 400072, registered with MahaRERA as P51800014134. It was launched in November 2017. It has 100 units in 1 building, with 1 and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in July 2022, after an extension of 1 year 6 months from the original January 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 10% complete.

100 units booked out of total 100 units (100%).