Lapsed

by Vardhan Housing · Chembur, Mumbai 400089 · Map

Launched
Nov 20175 yrs 1 mth originally promised
Possession (MahaRERA)
Jun 2024Extended by 1 yr 6 mthsWhat does Lapsed mean?
Concrete structure
50%Mid-construction
Booked
223 of 30573%
Buildings
21.2 acres
MahaRERA complaints
8Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
302
Other units
3
Total units
305
Buildings
2
Land
1.2 acres
Phases
1
MahaRERA complaints
8

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)50%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 50%Dec 2025: Concrete structure (RCC) 50%Jul 2026: Concrete structure (RCC) 50%Dec 2024: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 50%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%50%50%223
100%50%50%223
100%50%50%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Vardhan Heights by Vardhan Housing is a 305-unit SRA-sanctioned project in Chembur, Mumbai 400089, launched in November 2017; its MahaRERA registration has lapsed. 223 units booked out of total 305 units. The concrete structure (RCC) is 50% complete.

Read full summary

Vardhan Heights is an SRA-sanctioned project by Vardhan Housing in Chembur, Mumbai 400089, registered with MahaRERA as P51800014198. It was launched in November 2017. It has 305 units in 2 buildings: 302 homes (1 BHK) and 3 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in June 2024, after an extension of 1 year 6 months from the original December 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 50% complete, final finishes 50% complete.

223 units booked out of total 305 units (73%).