Redevelopment of Chandini CHS, Ghatkopar East
Lapsed
by Punjalal G Dave Realtors LLP · Ghatkopar East, Mumbai 400077 · Map
- Launched
- Dec 20173 yrs 6 mths originally promised
- Possession (MahaRERA)
- Dec 2021Extended by 6 mthsWhat does Lapsed mean?
- Concrete structure
- 80%Mid-construction
- Booked
- 9 of 1850%
- Buildings
- 10.3 acres
- MahaRERA complaints
- 0Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 7
- 3 BHK
- 11
- Total units
- 18
- Buildings
- 1
- Land
- 0.3 acres
- Phases
- 1
- MahaRERA complaints
- 0
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 80% | 80% | 9 | |
| 100% | 80% | 80% | 9 | |
| 100% | 80% | 80% | 9 |
"–" means MahaRERA shows no figure for that update.
About this project
Redevelopment of Chandini CHS by Punjalal G Dave Realtors LLP is an 18-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in December 2017; its MahaRERA registration has lapsed. 9 units booked out of total 18 units. The concrete structure (RCC) is 80% complete.
Read full summary
Redevelopment of Chandini CHS is a BMC-sanctioned project by Punjalal G Dave Realtors LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800014446. It was launched in December 2017. It has 18 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in December 2021, after an extension of 6 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 80% complete, final finishes 80% complete.
9 units booked out of total 18 units (50%).