Redevelopment of Chandini CHS, Ghatkopar East

Lapsed

by Punjalal G Dave Realtors LLP · Ghatkopar East, Mumbai 400077 · Map

Launched
Dec 20173 yrs 6 mths originally promised
Possession (MahaRERA)
Dec 2021Extended by 6 mthsWhat does Lapsed mean?
Concrete structure
80%Mid-construction
Booked
9 of 1850%
Buildings
10.3 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
7
3 BHK
11
Total units
18
Buildings
1
Land
0.3 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)80%
Finishes, lifts and services80%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 80%Dec 2025: Concrete structure (RCC) 80%Jul 2026: Concrete structure (RCC) 80%Dec 2024: Final finishes 80%Dec 2025: Final finishes 80%Jul 2026: Final finishes 80%Excavation 100%Concrete structure (RCC) 80%Final finishes 80%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%80%80%9
100%80%80%9
100%80%80%9

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Redevelopment of Chandini CHS by Punjalal G Dave Realtors LLP is an 18-unit BMC-sanctioned project in Ghatkopar East, Mumbai 400077, launched in December 2017; its MahaRERA registration has lapsed. 9 units booked out of total 18 units. The concrete structure (RCC) is 80% complete.

Read full summary

Redevelopment of Chandini CHS is a BMC-sanctioned project by Punjalal G Dave Realtors LLP in Ghatkopar East, Mumbai 400077, registered with MahaRERA as P51800014446. It was launched in December 2017. It has 18 units in 1 building, with 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2021, after an extension of 6 months from the original June 2021. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 80% complete, final finishes 80% complete.

9 units booked out of total 18 units (50%).