Blue Sapphire, Andheri East

Lapsed

by Blue Canyon Realty Pvt Ltd · Andheri East, Mumbai 400099 · Map

Launched
Jan 20182 yrs 3 mths originally promised
Possession (MahaRERA)
Feb 2024Extended by 3 yrs 10 mthsWhat does Lapsed mean?
Concrete structure
37%Mid-construction
Booked
5 of 2025%
Buildings
10.1 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 RK
1
1 BHK
12
2 BHK
7
Total units
20
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)37%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 37%Dec 2025: Concrete structure (RCC) 37%Jul 2026: Concrete structure (RCC) 37%Oct 2026: Concrete structure (RCC) 37%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Oct 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 37%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%37%0%5
100%37%0%–
100%37%0%–
100%37%0%5

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Blue Sapphire by Blue Canyon Realty Pvt Ltd is a 20-unit project in Andheri East, Mumbai 400099, launched in January 2018; its MahaRERA registration has lapsed. 5 units booked out of total 20 units. The concrete structure (RCC) is 37% complete.

Read full summary

Blue Sapphire is a project by Blue Canyon Realty Pvt Ltd in Andheri East, Mumbai 400099, registered with MahaRERA as P51800014896. It was launched in January 2018. It has 20 units in 1 building, with 1 RK, 1 BHK and 2 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in February 2024, after an extension of 3 years 10 months from the original April 2020. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) 37% complete, final finishes not started.

5 units booked out of total 20 units (25%).