Nandadeep Residency, Kurla West

Ready to moveLapsed

by Vinayaka Realtors And Developers · Kurla West, Mumbai 400070 · Map

Launched
Feb 20184 yrs 9 mths originally promised
Possession (MahaRERA)
Nov 2023Extended by 1 yrWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
18 of 2282%
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
20
Other units
2
Total units
22
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services90%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 90%Dec 2025: Final finishes 90%Jul 2026: Final finishes 90%Oct 2026: Final finishes 90%Excavation 100%Concrete structure (RCC) 100%Final finishes 90%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%90%18
100%100%90%–
100%100%90%–
100%100%90%18

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Nandadeep Residency by Vinayaka Realtors And Developers is a 22-unit project in Kurla West, Mumbai 400070, launched in February 2018; its MahaRERA registration has lapsed. 18 units booked out of total 22 units. The concrete structure (RCC) is complete.

Read full summary

Nandadeep Residency is a project by Vinayaka Realtors And Developers in Kurla West, Mumbai 400070, registered with MahaRERA as P51800015173. It was launched in February 2018. It has 22 units in 1 building: 20 homes (1 BHK) and 2 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in November 2023, after an extension of 1 year from the original November 2022. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.

18 units booked out of total 22 units (82%).