Twin Galaxy, Kurla West

by Twin Developers · Kurla West, Mumbai 400070 · Map

Launched
Feb 20184 yrs 10 mths originally promised
Possession (MahaRERA)
Dec 2027Extended by 5 yrs
Concrete structure
100%Nearing possession
Booked
135 of 13898%
Buildings
12.9 acres
MahaRERA complaints
1Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
20
2 BHK
99
3 BHK
19
Total units
138
Buildings
1
Land
2.9 acres
Phases
1
MahaRERA complaints
1

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services50%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 50%Dec 2025: Final finishes 50%Jul 2026: Final finishes 50%Oct 2026: Final finishes 50%Excavation 100%Concrete structure (RCC) 100%Final finishes 50%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%50%135
100%100%50%135
100%100%50%129
100%100%50%128

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400070

Projects with 60–300 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400070
MeasureThis projectSimilar projects
Launch to possession (as first promised)4 yrs 10 mths6 yrs 4 mths
Possession date extendedBy 5 yrs2 of 3
Possession date (MahaRERA)Dec 2027Dec 2024
Concrete structure (RCC)100%76%
MahaRERA complaints (filed by or against the builder)10

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Twin Galaxy by Twin Developers is a 138-unit SRA-sanctioned project in Kurla West, Mumbai 400070, launched in February 2018 with possession due in December 2027. 135 units booked out of total 138 units. The concrete structure (RCC) is complete.

Read full summary

Twin Galaxy is an SRA-sanctioned project by Twin Developers in Kurla West, Mumbai 400070, registered with MahaRERA as P51800015405. It was launched in February 2018. It has 138 units in 1 building, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Active.

Its registered possession date is December 2027, extended by 5 years from the original December 2022. Construction: excavation complete, structure (RCC) complete, final finishes 50% complete.

135 units booked out of total 138 units (98%).