Dsk Madhukosh, Kurla West

Lapsed

by D S Kulkarni Developers Limited · Kurla West, Mumbai 400070 · Map

Launched
Aug 20171 yr 8 mths promised
Possession (MahaRERA)
Apr 2019Not extendedWhat does Lapsed mean?
Concrete structure
53%Mid-construction
Booked
126 of 17074%
Buildings
31.3 acres
MahaRERA complaints
18Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

1 BHK
12
2 BHK
156
3 BHK
2
Total units
170
Buildings
3
Land
1.3 acres
Phases
1
MahaRERA complaints
18

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)53%
Finishes, lifts and services60%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 53%Dec 2025: Concrete structure (RCC) 53%Jul 2026: Concrete structure (RCC) 53%Oct 2026: Concrete structure (RCC) 53%Dec 2024: Final finishes 60%Dec 2025: Final finishes 60%Jul 2026: Final finishes 60%Oct 2026: Final finishes 60%Excavation 100%Final finishes 60%Concrete structure (RCC) 53%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%53%60%126
100%53%60%126
100%53%60%–
100%53%60%127

"–" means MahaRERA shows no figure for that update.

How to read construction stages

Compared with 3 similar projects in PIN 400070

Projects with 80–350 flats, launched within 6 months of this one.

Compared with 3 similar projects in PIN 400070
MeasureThis projectSimilar projects
Launch to possession (as first promised)1 yr 8 mths6 yrs 4 mths
Possession date extendedNo3 of 3
Possession date (MahaRERA)Apr 2019Dec 2026
Concrete structure (RCC)53%100%
MahaRERA complaints (filed by or against the builder)180

The 3 projects

Other phases of this project are not included in the similar projects.

About this project

Dsk Madhukosh by D S Kulkarni Developers Limited is a 170-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in August 2017; its MahaRERA registration has lapsed. 126 units booked out of total 170 units. The concrete structure (RCC) is 53% complete.

Read full summary

Dsk Madhukosh is a BMC-sanctioned project by D S Kulkarni Developers Limited in Kurla West, Mumbai 400070, registered with MahaRERA as P51800009465. It was launched in August 2017. It has 170 units in 3 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in April 2019. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 53% complete, final finishes 60% complete.

126 units booked out of total 170 units (74%).