- Launched
- Aug 20171 yr 8 mths promised
- Possession (MahaRERA)
- Apr 2019Not extendedWhat does Lapsed mean?
- Concrete structure
- 53%Mid-construction
- Booked
- 126 of 17074%
- Buildings
- 31.3 acres
- MahaRERA complaints
- 18Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 12
- 2 BHK
- 156
- 3 BHK
- 2
- Total units
- 170
- Buildings
- 3
- Land
- 1.3 acres
- Phases
- 1
- MahaRERA complaints
- 18
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 53% | 60% | 126 | |
| 100% | 53% | 60% | 126 | |
| 100% | 53% | 60% | – | |
| 100% | 53% | 60% | 127 |
"–" means MahaRERA shows no figure for that update.
Compared with 3 similar projects in PIN 400070
Projects with 80–350 flats, launched within 6 months of this one.
| Measure | This project | Similar projects |
|---|---|---|
| Launch to possession (as first promised) | 1 yr 8 mths | 6 yrs 4 mths |
| Possession date extended | No | 3 of 3 |
| Possession date (MahaRERA) | Apr 2019 | Dec 2026 |
| Concrete structure (RCC) | 53% | 100% |
| MahaRERA complaints (filed by or against the builder) | 18 | 0 |
The 3 projects
- Tanishq Residency, Kurla West
- Khaliliya Complex, Kurla West
- Twin Galaxy, Kurla West
Other phases of this project are not included in the similar projects.
| Project | Launched | Possession date (MahaRERA) | Concrete structure (RCC) | Units booked |
|---|---|---|---|---|
| Tanishq Residency | August 2017 | December 2024 | 100% | – |
| Khaliliya Complex | August 2017 | December 2026 | 76% | – |
| Twin Galaxy | February 2018 | December 2027 | 100% | 135 units booked out of total 138 units |
About this project
Dsk Madhukosh by D S Kulkarni Developers Limited is a 170-unit BMC-sanctioned project in Kurla West, Mumbai 400070, launched in August 2017; its MahaRERA registration has lapsed. 126 units booked out of total 170 units. The concrete structure (RCC) is 53% complete.
Read full summary
Dsk Madhukosh is a BMC-sanctioned project by D S Kulkarni Developers Limited in Kurla West, Mumbai 400070, registered with MahaRERA as P51800009465. It was launched in August 2017. It has 170 units in 3 buildings, with 1, 2 and 3 BHK homes as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in April 2019. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 53% complete, final finishes 60% complete.
126 units booked out of total 170 units (74%).