Platina, Khar West
Ready to moveLapsed
by G F Reality Private Limited · Khar West, Mumbai 400052 · Map
- Launched
- Mar 20181 yr 9 mths originally promised
- Possession (MahaRERA)
- Jun 2025Extended by 5 yrs 6 mthsWhat does Lapsed mean?
- Concrete structure
- 100%Ready to move
- Booked
- 10 of 4323%
- Buildings
- 10.1 acres
- MahaRERA complaints
- 3Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 1 BHK
- 18
- 2 BHK
- 5
- 3 BHK
- 3
- Other units
- 17
- Total units
- 43
- Buildings
- 1
- Land
- 0.1 acres
- Phases
- 1
- MahaRERA complaints
- 3
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 100% | 100% | 90% | 10 | |
| 100% | 100% | 90% | – | |
| 100% | 100% | 90% | – | |
| 100% | 90% | 50% | 10 |
"–" means MahaRERA shows no figure for that update.
About this project
Platina by G F Reality Private Limited is a 43-unit BMC-sanctioned project in Khar West, Mumbai 400052, launched in March 2018; its MahaRERA registration has lapsed. 10 units booked out of total 43 units. The concrete structure (RCC) is complete.
Read full summary
Platina is a BMC-sanctioned project by G F Reality Private Limited in Khar West, Mumbai 400052, registered with MahaRERA as P51800015512. It was launched in March 2018. It has 43 units in 1 building: 26 homes (1, 2 and 3 BHK) and 17 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in June 2025, after an extension of 5 years 6 months from the original December 2019. That date has passed and no further extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 90% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.
10 units booked out of total 43 units (23%).