Meeras Empire And Meeras Crown, Goregaon West

Lapsed

by Rushabh Real Estate Developers Private Limited · Goregaon West, Mumbai 400090 · Map

Launched
Mar 20185 yrs 8 mths promised
Possession (MahaRERA)
Nov 2023Not extendedWhat does Lapsed mean?
Concrete structure
28%Mid-construction
Booked
–
Buildings
31.6 acres
MahaRERA complaints
4Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

2 BHK
72
3 BHK
38
Other units
163
Total units
273
Buildings
3
Land
1.6 acres
Phases
1
MahaRERA complaints
4

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation28%
Concrete structure (slabs)28%
Finishes, lifts and services28%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 28%Dec 2025: Excavation 28%Jul 2026: Excavation 28%Dec 2024: Concrete structure (RCC) 28%Dec 2025: Concrete structure (RCC) 28%Jul 2026: Concrete structure (RCC) 28%Dec 2024: Final finishes 28%Dec 2025: Final finishes 28%Jul 2026: Final finishes 28%Excavation 28%Concrete structure (RCC) 28%Final finishes 28%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
28%28%28%–
28%28%28%–
28%28%28%86

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Meeras Empire And Meeras Crown by Rushabh Real Estate Developers Private Limited is a 273-unit project in Goregaon West, Mumbai 400090, launched in March 2018; its MahaRERA registration has lapsed. The concrete structure (RCC) is 28% complete.

Read full summary

Meeras Empire And Meeras Crown is a project by Rushabh Real Estate Developers Private Limited in Goregaon West, Mumbai 400090, registered with MahaRERA as P51800015541. It was launched in March 2018. It has 273 units in 3 buildings: 110 homes (2 and 3 BHK) and 163 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in November 2023. That date has passed and no extension has been recorded. Construction: excavation 28% complete, structure (RCC) 28% complete, final finishes 28% complete.