Meeras Empire And Meeras Crown, Goregaon West
Lapsed
by Rushabh Real Estate Developers Private Limited · Goregaon West, Mumbai 400090 · Map
- Launched
- Mar 20185 yrs 8 mths promised
- Possession (MahaRERA)
- Nov 2023Not extendedWhat does Lapsed mean?
- Concrete structure
- 28%Mid-construction
- Booked
- –
- Buildings
- 31.6 acres
- MahaRERA complaints
- 4Filed by or against the builder
Shortlist 2 or more to compare side by side.
Project facts
- 2 BHK
- 72
- 3 BHK
- 38
- Other units
- 163
- Total units
- 273
- Buildings
- 3
- Land
- 1.6 acres
- Phases
- 1
- MahaRERA complaints
- 4
Construction progress
As reported by the builder to MahaRERA (whole project)
How construction has progressed
Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.
Updates reported to MahaRERA
| Update | Excavation | Structure (RCC) | Final finishes | Units booked |
|---|---|---|---|---|
| 28% | 28% | 28% | – | |
| 28% | 28% | 28% | – | |
| 28% | 28% | 28% | 86 |
"–" means MahaRERA shows no figure for that update.
About this project
Meeras Empire And Meeras Crown by Rushabh Real Estate Developers Private Limited is a 273-unit project in Goregaon West, Mumbai 400090, launched in March 2018; its MahaRERA registration has lapsed. The concrete structure (RCC) is 28% complete.
Read full summary
Meeras Empire And Meeras Crown is a project by Rushabh Real Estate Developers Private Limited in Goregaon West, Mumbai 400090, registered with MahaRERA as P51800015541. It was launched in March 2018. It has 273 units in 3 buildings: 110 homes (2 and 3 BHK) and 163 other units (shops, offices or not given by type), as registered with MahaRERA. Its MahaRERA status is Lapsed.
Possession was due in November 2023. That date has passed and no extension has been recorded. Construction: excavation 28% complete, structure (RCC) 28% complete, final finishes 28% complete.