Innovative Infopark, Jogeshwari East

Ready to moveLapsed

by Khushi Developers · Jogeshwari East, Mumbai 400060 · Map

Launched
May 20181 yr 3 mths promised
Possession (MahaRERA)
Aug 2019Not extendedWhat does Lapsed mean?
Concrete structure
100%Ready to move
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
12
Total units
12
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)100%
Finishes, lifts and services95%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Oct 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Oct 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 100%Dec 2025: Concrete structure (RCC) 100%Jul 2026: Concrete structure (RCC) 100%Oct 2026: Concrete structure (RCC) 100%Dec 2024: Final finishes 95%Dec 2025: Final finishes 95%Jul 2026: Final finishes 95%Oct 2026: Final finishes 95%Excavation 100%Concrete structure (RCC) 100%Final finishes 95%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%100%95%–
100%100%95%–
100%100%95%–
100%100%95%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Innovative Infopark by Khushi Developers is a 12-unit project in Jogeshwari East, Mumbai 400060, launched in May 2018; its MahaRERA registration has lapsed. The concrete structure (RCC) is complete.

Read full summary

Innovative Infopark is a project by Khushi Developers in Jogeshwari East, Mumbai 400060, registered with MahaRERA as P51800016285. It was launched in May 2018. It has 12 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in August 2019. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) complete, final finishes 95% complete. Final finishes are 90% or more complete; completion has not yet been recorded on MahaRERA.