Lapsed

by Aadi Properties LLP · Bhandup East, Mumbai 400042 · Map

Launched
May 20186 yrs 7 mths promised
Possession (MahaRERA)
Dec 2024Not extendedWhat does Lapsed mean?
Concrete structure
10%Mid-construction
Booked
–
Buildings
10.1 acres
MahaRERA complaints
0Filed by or against the builder
WhatsApp

Shortlist 2 or more to compare side by side.

Project facts

Other units
102
Total units
102
Buildings
1
Land
0.1 acres
Phases
1
MahaRERA complaints
0

Construction progress

As reported by the builder to MahaRERA (whole project)

Excavation100%
Concrete structure (slabs)10%
Finishes, lifts and services0%

How construction has progressed

Each point is the progress shown on MahaRERA at that update. A line that stays flat means no new progress was reported between two dates.

Concrete structure (RCC)Final finishesExcavation
0%25%50%75%100%Dec 2024Dec 2025Jul 2026Dec 2024: Excavation 100%Dec 2025: Excavation 100%Jul 2026: Excavation 100%Dec 2024: Concrete structure (RCC) 10%Dec 2025: Concrete structure (RCC) 10%Jul 2026: Concrete structure (RCC) 10%Dec 2024: Final finishes 0%Dec 2025: Final finishes 0%Jul 2026: Final finishes 0%Excavation 100%Concrete structure (RCC) 10%Final finishes 0%

Updates reported to MahaRERA

Updates reported to MahaRERA, newest first
UpdateExcavationStructure (RCC)Final finishesUnits booked
100%10%0%–
100%10%0%–
100%10%0%0

"–" means MahaRERA shows no figure for that update.

How to read construction stages

About this project

Allure Commercial by Aadi Properties LLP is a 102-unit project in Bhandup East, Mumbai 400042, launched in May 2018; its MahaRERA registration has lapsed. The concrete structure (RCC) is 10% complete.

Read full summary

Allure Commercial is a project by Aadi Properties LLP in Bhandup East, Mumbai 400042, registered with MahaRERA as P51800016566. It was launched in May 2018. It has 102 units in 1 building, as registered with MahaRERA. Its MahaRERA status is Lapsed.

Possession was due in December 2024. That date has passed and no extension has been recorded. Construction: excavation complete, structure (RCC) 10% complete, final finishes not started.